Parking Garage
Milestone timeline:
June 2020
Schematic Design Review at 3 stories (4 levels)
Completed: Jun 4, 2020
October 2020
Site Plan Approved
Completed: Oct 1, 2020
July 2021
Finalized Design & Permitting
Completed: Jul 1, 2021
September 2021
Start of Demolition of Existing Buildings
Completed: Sep 7, 2021
September 2021
Guaranteed Maximum Price
Completed: Sep 22, 2021
November 2021
Construction Scheduled to Begin
Completed: Sep 22, 2021
April 2022
Evening Church St. Closure Starts April 11
Completed: Apr 29, 2022
July 11, 2022
Crane Assembly On-Site
Completed: Jul 11, 2022
July 18, 2022
Begin Installation of Precast Sections
Completed: Jul 18, 2022
Fall 2022
Parking Kiosks Installed in Downtown
January 2023
Estimated Substantial Project Completion
February / March 2023
Garage Opens and Metering Begins

Project Updates:
Downtown Parking Background & Updates
In 2022, the Downtown Parking Garage at the corner of 5th Avenue and Church Street is under construction. Concurrently with the garage, a comprehensive parking management update will address demand for on-street parking and off-street, permitted parking. A 3-story (4-level) garage is underway at the corner of 5th Avenue and Church Street.
Architect
Walker Consultants
Construction Manager at Risk
Edifice General Contractors