Sullivan Park Basketball Court Rehabilitation

Milestone timeline:

Grant Acceptance
Completed: Jul 2, 2025
Summer 2025
Sullivan Park Courts Closed for Rehab
Completed: Jul 18, 2025
Summer 2025
Sponsorship Acceptance
Completed: Jul 23, 2025
Summer 2025
Construction Begins
Completed: Jul 28, 2025
July 28, 2025
Anticipated Reopening of Courts
September 10, 2025

The Sullivan Park basketball courts on Ashe Street in Hendersonville are being resurfaced and improved! 

The Sullivan Park goals have been removed in preparation of construction that is expected to start on July 28th. The courts will be closed until mid-September to allow the resurfacing project to occur. An announcement will be made later in the summer with details about the grant that is making the improvements possible. 

The City of Hendersonville’s Public Works Department is managing the rehabilitation of the court’s surface and basketball goals. The court has developed cracks, and the rehabilitation process will include grinding down the old asphalt and replacing it with a new court surface. Updated backboards will also be installed as part of the project. 

We appreciate the community’s patience while we make improvements to the courts! 

Project Updates: 
Court Rehabilitation in Progress
Thursday, July 31, 2025

paving equipment resurfacing a covered basketball court

Grant Approval Resolution
Wednesday, July 23, 2025

The Hendersonville City Council approved the grant and sponsorships for the Sullivan Park basketball court project on July 23, 2025.

View the agenda packet for additional details